Verification and Validation
National Aeronautics and Space
Administration A. Concepts and
Definitions
Software Verification and Validation (V&V) is the
process of ensuring that software being developed or
changed will satisfy functional and other requirements
(validation) and each step in the process of building the
software yields the right products (verification). The
differences between verification and validation are
unimportant except to the theorist; practitioners’
use the term V&V to refer to all of the activities
devoted to making sure the software will function as
required.
V&V is a systematic and technical evaluation of
software and associated products of the development and
maintenance processes. Reviews and tests at the end of
each phase of the development process ensure software
requirements are complete and testable and that design,
code, documentation, and data satisfy those
requirements.
B. Activities
The two major V&V activities are reviews, including
inspections and walkthroughs, and testing.
- Reviews, Inspections, and Walkthroughs
- Reviews are conducted during and at the end of
each phase of the life cycle to determine whether
established requirements, design concepts, and
specifications have been met. Reviews consist of
the presentation of material to a review board or
panel. Reviews are most effective when conducted by
personnel who have not been directly involved in
the development of the software being
reviewed.
- Informal reviews are conducted on an as-needed
basis. The developer chooses a reviewer or review
panel and provides and/or presents the material to
be reviewed. The material may be as informal as a
computer listing or hand-written
documentation.
- Formal reviews are conducted at the end of each
life cycle phase. The acquirer of the software
appoints the formal review panel or board, who may
make or affect a go/no-go decision to proceed to
the next step of the life cycle. Formal reviews
include the Software Requirements Review, the
Software Preliminary Design Review, the Software
Critical Design Review, and the Software Test
Readiness Review.
- An inspection or walkthrough is a detailed
examination of a product on a step-by-step or
line-of-code by line-of-code basis. The purpose of
conducting inspections and walkthroughs is to find
errors. The group that does an inspection or
walkthrough is composed of peers from development,
test, and quality assurance.
- Testing
Testing is the operation of the software with real or
simulated inputs to demonstrate that a product
satisfies its requirements and, if it does not, to
identify the specific differences between expected
and actual results. There are varied levels of
software tests, ranging from unit or element testing
through integration testing and performance testing,
up to software system and acceptance tests.
- Informal Testing
Informal tests are done by the developer to
measure the development progress.
“Informal” in this case does not mean
that the tests are done in a casual manner, just
that the acquirer of the software is not formally
involved, that witnessing of the testing is not
required, and that the prime purpose of the tests
is to find errors. Unit, component, and subsystem
integration tests are usually informal tests.
Informal testing may be requirements-driven or
design-driven. Requirements-driven or black box
testing is done by selecting the input data and
other parameters based on the software
requirements and observing the outputs and
reactions of the software. Black box testing can
be done at any level of integration. In addition
to testing for satisfaction of requirements, some
of the objectives of requirements-driven testing
are to ascertain:
- Computational correctness.
- Proper handling of boundary conditions,
including extreme inputs and conditions that
cause extreme outputs.
- State transitioning as expected.
- Proper behavior under stress or high
load.
- Adequate error detection, handling, and
recovery.
Design-driven or white box testing is the
process where the tester examines the internal
workings of code. Design-driven testing is done
by selecting the input data and other parameters
based on the internal logic paths that are to be
checked. The goals of design-driven testing
include ascertaining correctness of:
- All paths through the code. For most
software products, this can be feasibly done
only at the unit test level.
- Bit-by-bit functioning of interfaces.
- Size and timing of critical elements of
code.
- Formal Tests
Formal testing demonstrates that the software is
ready for its intended use. A formal test should
include an acquirer-approved test plan and
procedures, quality assurance witnesses, a record
of all discrepancies, and a test report. Formal
testing is always requirements-driven, and its
purpose is to demonstrate that the software meets
its requirements.
Each software development project should have at
least one formal test, the acceptance test that
concludes the development activities and
demonstrates that the software is ready for
operations.
In addition to the final acceptance test, other
formal testing may be done on a project. For
example, if the software is to be developed and
delivered in increments or builds, there may be
incremental acceptance tests. As a practical
matter, any contractually required test is usually
considered a formal test; others are
“informal.”
After acceptance of a software product, all changes
to the product should be accepted as a result of a
formal test. Post acceptance testing should include
regression testing. Regression testing involves
rerunning previously used acceptance tests to
ensure that the change did not disturb functions
that have previously been accepted.
C. Verification and
Validation
During the Software Acquisition Life Cycle The V&V
Plan should cover all V&V activities to be performed
during all phases of the life cycle. The V&V Plan
Data Item Description (DID) may be rolled out of the
Product Assurance Plan DID contained in the SMAP
Management Plan Documentation Standard and DID.
- Software Concept and Initiation Phase
The major V&V activity during this phase is to
develop a concept of how the system is to be reviewed
and tested. Simple projects may compress the life cycle
steps; if so, the reviews may have to be compressed.
Test concepts may involve simple generation of test
cases by a user representative or may require the
development of elaborate simulators and test data
generators. Without an adequate V&V concept and
plan, the cost, schedule, and complexity of the project
may be poorly estimated due to the lack of adequate
test capabilities and data.
- Software Requirements Phase
V&V activities during this phase should include:
Analyzing software requirements to determine if they
are consistent with, and within the scope of, system
requirements. Assuring that the requirements are
testable and capable of being satisfied. Creating a
preliminary version of the Acceptance Test Plan,
including a verification matrix, which relates
requirements to the tests used to demonstrate that
requirements are satisfied. Beginning development, if
needed, of test beds and test data generators. The
phase-ending Software Requirements Review (SRR).
- Software Architectural (Preliminary) Design
Phase
V&V activities during this phase should include:
Updating the preliminary version of the Acceptance Test
Plan and the verification matrix. Conducting informal
reviews and walkthroughs or inspections of the
preliminary software and data base designs. The
phase-ending Preliminary Design Review (PDR) at which
the allocation of requirements to the software
architecture is reviewed and approved.
- Software Detailed Design Phase
V&V activities during this phase should include:
Completing the Acceptance Test Plan and the
verification matrix, including test specifications and
unit test plans. Conducting informal reviews and
walkthroughs or inspections of the detailed software
and data base designs. The Critical Design Review (CDR)
which completes the software detailed design
phase.
- Software Implementation Phase
V&V activities during this phase should include:
Code inspections and/or walkthroughs. Unit testing
software and data structures. Locating, correcting, and
retesting errors. Development of detailed test
procedures for the next two phases.
- Software Integration and Test Phase
This phase is a major V&V effort, where the tested
units from the previous phase are integrated into
subsystems and then the final system. Activities during
this phase should include: Conducting tests per test
procedures. Documenting test performance, test
completion, and conformance of test results versus
expected results. Providing a test report that includes
a summary of non-conformances found during testing.
Locating, recording, correcting, and retesting
non-conformances. The Test Readiness Review (TRR),
confirming the product’s readiness for acceptance
testing.
- Software Acceptance and Delivery Phase
V&V activities during this phase should include: By
test, analysis, and inspection, demonstrating that the
developed system meets its functional, performance, and
interface requirements. Locating, correcting, and
retesting non-conformances. The phase-ending Acceptance
Review (AR).
- Software Sustaining Engineering and Operations
Phase
Any V&V activities conducted during the prior seven
phases are conducted during this phase as they pertain
to the revision or update of the software.
D. Independent Verification and
Validation
Independent Verification and Validation (IV&V) is a
process whereby the products of the software development
life cycle phases are independently reviewed, verified,
and validated by an organization that is neither the
developer nor the acquirer of the software. The IV&V
agent should have no stake in the success or failure of
the software. The IV&V agent’s only interest
should be to make sure that the software is thoroughly
tested against its complete set of requirements.
The IV&V activities duplicate the V&V activities
step-by-step during the life cycle, with the exception
that the IV&V agent does no informal testing. If
there is an IV&V agent, the formal acceptance testing
may be done only once, by the IV&V agent. In this
case, the developer will do a formal demonstration that
the software is ready for formal acceptance.
E. Techniques and Tools
Perhaps more tools have been developed to aid the V&V
of software (especially testing) than any other software
activity. The tools available include code tracers,
special purpose memory dumpers and formatters, data
generators, simulations, and emulations. Some tools are
essential for testing any significant set of software,
and, if they have to be developed, may turn out to be a
significant cost and schedule driver.
An especially useful technique for finding errors is the
formal inspection. Formal inspections were developed by
Michael Fagan of IBM. Like walkthroughs, inspections
involve the line-by-line evaluation of the product being
reviewed. Inspections, however, are significantly
different from walkthroughs and are significantly more
effective. Inspections are done by a team, each member of
which has a specific role. The team is led by a
moderator, who is formally trained in the inspection
process. The team includes a reader, who leads the team
through the item; one or more reviewers, who look for
faults in the item; a recorder, who notes the faults; and
the author, who helps explain the item being
inspected.
This formal, highly structured inspection process has
been extremely effective in finding and eliminating
errors. It can be applied to any product of the software
development process, including documents, design, and
code. One of its important side benefits has been the
direct feedback to the developer/author, and the
significant improvement in quality that results.